Progress certificate (acta de obra)

A progress certificate, called acta de obra or acta de corte in Colombia, is the document in which the contractor and the supervising engineer or the owner record the quantities of work executed in a period, priced at the contract’s unit prices. It is the basis for invoicing and collecting what was built.

On a road project, the resident engineer and the inspector measure each item at the work front, by station, and carry those quantities to a draft certificate. The supervising engineer reviews it, both parties sign it and the progress certificate follows, which is used to invoice. Each certificate deducts the amortization of the advance payment and, when the contract requires it, the retention.

If the contractor was not present at the measurement, the supervisor’s quantity stands, and work done that wasn’t noted at the front never makes it into the certificate. When an invoice goes out without the signed draft, the owner returns it in full. Work that was actually built goes unbilled, and collection is delayed.

DataNova records each quantity at the work front the same day, from a phone, with photo and time. The draft certificate is signed in the field by both parties, the invoice goes out with the approved certificate and each filed certificate carries its contractual payment date. The advance balance goes down with each certificate, and any quantity in the lender report opens down to the field record.